Kelesi Environmental Incident Emergency Drill Summary Report
2023-07-04 13:36
In order to effectively prevent, control and promptly eliminate the occurrence of environmental accidents, improve the ability to deal with environmental pollution accident rescue and emergency response, establish and improve environmental early warning and emergency response mechanisms, and ensure the safe and stable operation of the company's production, according to the relevant documents of the Ministry of Safety and Environmental Protection In accordance with the spiritual requirements and based on the actual situation of the company, the "Chemical Leak Emergency Drill" was organized and implemented. The activities are summarized as follows:
1. Exercise time: April 17, 2023, 12:00-14:00;
2. Drill content: Emergency response to polymethylmethacrylate leakage;
3. Drill location: 3# workshop transfer warehouse entrance
4. Meeting place: 3# workshop transfer warehouse
5. Participants: production department employee representatives, team leaders and above, general department managers, warehouse administrators, and quality control department managers.
6. Drill content: Employees entered the transfer area after receiving polymethyl methacrylate from the warehouse. Due to damage to the feet of the ton barrel, the dumping liquid leaked from the ton barrel and flowed in all directions at the gate of the transfer area. The employee involved shouted loudly to inform his colleagues in the same position, and at the same time took sand and soil from the emergency sandbox to contain it. Due to the failure to contain it in time, part of the polymethyl methacrylate overflowed from the workshop to the rainwater pipe, so he immediately notified the department manager and the company Relevant personnel participated in the rescue, rescue, and repair drills.
1. Preparation for drills
Prepare the materials needed for this drill: two buckets of clean water, one emergency sandbag, two forklifts, and one ton bucket (empty bucket).
Before the drill, the manager of the Safety and Environmental Protection Department explained the purpose of the emergency drill, the responsibilities and work arrangements of each emergency team, the precautions for emergency response at the scene of a hazardous chemical leakage accident, and the drill process for handling the chemical leakage accident.
2. Exercise content
1. Operator Liu Futao encountered a danger during the operation. He immediately shouted to the team leader Liu Quanguo to get emergency sand to contain it, and immediately called the assistant manager Zhang Yongbin to arrange personnel support.
2. After receiving the notice, the assistant manager Zhang Yongbin immediately organized the shift director Li Chunliang to lead the employees on duty to the accident site to assist in the rescue; at the same time, he notified the department manager Yu Lin by phone to act as on-site command before the department manager arrived at the accident site.
3. Assistant manager Wang Xiaoming notified the mobile team Zhang Wei to transport emergency sandbags and rush to the accident site.
4. Due to the lack of timely containment, some polymethyl methacrylate overflowed from the workshop into the rainwater pipes.
5. The production manager rushed to the scene to set up a command team and arranged for assistant manager Zhang Yongbin to organize personnel to close the stop valve of the rainwater discharge outlet in the northeast corner of the factory to prevent the leakage of pollutants.
6. Switch the accident pool switching valve to the accident pool flow direction to allow pollutants to flow into the accident pool.
7. The on-site environmental monitoring team arranged for personnel to continue to pay attention to the water quality until the water quality was restored before restoring the positions of the accident pool switching valve and the rainwater discharge stop valve.
8. The on-site environmental monitoring team arranged for personnel to continue to pay attention to the water quality until the water quality was restored before restoring the positions of the accident pool switching valve and the rainwater discharge stop valve.
3. Exercise summary and evaluation
Evaluate the effectiveness of this drill, emphasizing that if a chemical leak occurs, it must first be reported immediately, and the department manager shall act as the commander-in-chief to coordinate and deal with it, and secondly, the stop valve of the rainwater discharge outlet must be closed immediately to prevent the leakage of pollutants from spreading to the contaminated area. Control within the factory area and organize compliance disposal.
This activity basically achieved the purpose of the drill. All relevant personnel arrived at the gathering place on time. Each group of personnel acted quickly and carried out rescue activities in an orderly manner according to their respective drill responsibilities.
Process issues:
1. The coordination of mutual cooperation between personnel needs to be improved. 2. The speed of rescuers arriving at the scene needs to be improved.
Improvements:
In future work and emergency activities, deficiencies will be improved, emergency response training will be further strengthened, and the feasibility of emergency plans will be improved.